nrt1 extreme latency; Terra maneuver at 00:10z

PlatformTerra-Aqua
InstrumentMODIS
Sourcelance-modis
Issuenews
Last Updated2015-06-17 00:33:00
Start2015-06-14 19:00:00
End2015-06-15 13:38:00
Description 2015-06-17T00:33:00Z
Our nrt1 processing system was essentially down between 2015-06-14 19:00z and 2015-06-15 13:38z due to network issues. nrt1 processing has as of this time almost caught up with processing on the backup nrt2 system (distributed via nrt2.modaps.eosdis.nasa.gov).

Also a Terra DMU #93/RMM#11 maneuver has been scheduled for 00:10-03:40z (right about now) and could as usual with Terra maneuvers cause some granules to be not produced or be of low quality.

We normally don't announce maneuvers and related granule production and quality issues in this email list, but are doing so tonight since an email is already going out and this maneuver was announced with only a days notice.